PROGRESS
9%
Over all Progress
16% Structure | 0% Architecture | 0% Engineering
B building large-scale concrete cap, About 7,600 cubic meters, about 36 hours of pouring, this month on the 6th of this month, the caisson of the deep foundation pit, about 800 cubic meters.
Building A area elevator shaft. Overall progress, the site construction was about 15 days ahead of schedule