PROGRESS
22%
30% Structure | 0% Architecture | 5% Engineering
 

Tower A : 6th Floor +20.20m install formwork, rebar & PT

Tower B : 7th Floor +23.45m install formwork                   

Carpark : Zone1 & Zone2 7B +21.50m slab GL M-L&R / 6-9 Install formwork & rebar

 

APRIL 2019